Lefilter2024-10-18 BACK TO LIST
1、Check the installation ground:The ground is required to be flat, and the flatness is required to be less than 10mm/per metre; the cement ground is required to have a bearing weight of more than 3 tonnes/square metre.
2、Arrangement of LFQ units:Arrange the LFQ units in accordance with the installation drawings.
3、Installation of sewage valve.
4、Installation of inlet and outlet drainage pipe. (When installing, pay attention to protect the plastic drain valve, so as not to touch the broken can be installed bracket to support the main pipe)
5、Installation of differential pressure switch, inlet and outlet water pressure gauge and exhaust valve, pay attention to the threaded interface, so as not to connect the wrong.
6, to the LFQ unit wiring and piping